Wayland High School Building Committee
Wayland High School Building Committee
About the Project
11/9/09 - New Appropriation History Chart -scroll down to see
Project Budget
Administration
Architecture & Engineering
Construction
Furnishings & Equipment
Miscellaneous
Owner's Contingency
Total Project Budget
Ineligible and Excluded Items
Waste Water Treatment
Site Improvements
Additional Contingency
Asbestos Abatement
Permits, Moving & Storage, Other
Total Ineligible and Excluded
Grant Eligible Costs
Total MSBA Grant (40%)
Wayland’s Share of Total Project Budget
Detail of Total Proposed Project Budget -
as approved by MSBA on 9/30/09
During Construction Period
(FY 2011 to FY2012)
Greatest One-Year Impact
(FY2013)
5 Yrs Following Full Bond Issuance
(FY 2013 to FY2017)
Over The Life of the Bonds
(FY2011 to FY2037)
Avg. Annual % Impact on Tax Rate (note 2)
2.79%
6.22%
5.98%
4.54%
Avg. Annual Per $100K of Home Value
$46
$102
$98
$74
Avg. Annual Per Average Home Value @ $650K
$296
$661
$636
$483
Incremental Property Tax Impact Metrics (note 1)
Source: Finance Committee 10-19-09
Notes:
(1) Long-term bonds will be issued annually during construction at an estimated composite interest rate of 3.5%. These bonds will be repaid or amortized over 25 years. Model assumes $10M issued in FY11, $20M issued in FY12 and $15.5M issued in FY13 totaling $45.15M in bonds.
(2)FY10 tax rate is $16.37 per $1,000 of assessed value.
(3)The Community Preservation Assessment (CPA) surcharge of 1.5% on property tax amounts in not included above.
Recap of Appropriation History
Note from the HSBC: The “Avg. Annual % Impact” is expressed as a percentage of the 2009 tax bill; for example, the annual % impact in FY2013 is 6.22% of the 2009 tax bill, not the 2013 tax bill.
Link to the Finance Committee’s WHS Tax Impact Analysis here.