REPORT OF THE HIGH SCHOOL BUILDING COMMITTEE

April  2009

 

This update describes the work of the High School Building Committee (HSBC) during the past year, since the Annual Town Meeting on April 10, 2008.  It also reviews the steps taken with the Massachusetts School Building Authority (MSBA) since the lifting of the  moratorium on state funding in 2007.

 

The work of the HSBC in prior years is summarized in the Report of the HSBC published in the January 2005 Special Town Meeting Warrant.  It and the more extensive 2004 Preliminary Design Report are both available on the HSBC web site (www.waylandschoolcommittee.org/whs/hsbc/index.htm) and at the Wayland Public Library.

 

Over the past year, the HSBC met 13 times for a total of 65 meetings since January 2004. These most recent meetings focused on the required steps leading to the Feasibility Study/Schematic Design phase defined by the MSBA.  Specifically, the HSBC:

 

Massachusetts School Building Authority (MSBA) Ð MSBA regulations define a five-phase process, with guidelines that clearly define the components, their sizes, and their characteristics for which the state will provide reimbursement..  The state and local community will work together at every step of the new process.  The five phases are:  identify the problem, validate the problem, evaluate potential solutions, confirm a solution, and implement the agreed upon solution.

 

Identify the Problem (Statement of Interest) Ð The Wayland School Committee and Board of Selectmen submitted a Statement of Interest (SOI) to the Massachusetts School Building Authority in August, 2006.  The SOI was the first step in the application process for state funding.  Communities were asked to document deficiencies under eight statutory criteria: health and safety, existing severe overcrowding, loss of accreditation, prevention of future severe overcrowding, energy conservation and decreased energy costs, short term enrollment growth, replacement of obsolete buildings, and transition from court ordered racial balance districts to walk-to districts.  Wayland documented deficiencies in seven of the eight statutory criteria.

 

Validate the Problem - The MSBA visited Wayland High School three times during 2007. 

 

Enrollment Site Visit and Review Ð In June, 2007, MSBA consultants toured Wayland High School to see firsthand the conditions of overcrowding.  They were shown many spaces that have been converted from a previous use, such as a staff dining room converted to a student cafeteria annex, reference centers converted to classrooms, a furnace room converted to a health classroom, and TEC (The Education Collaborative) space converted to classrooms.   They were also shown many significantly undersized classrooms, science labs, modular science building, auditorium, and locker rooms relative to current MSBA standards.

 

Facilities and Maintenance Assessment Ð In June, 2007, Joseph Buckley, P.E., Chief Engineer for the MSBA, and ten other architects and engineers came to Wayland to begin a three day study of all five schools as part of the Facilities and Maintenance Assessment.  Wayland was one of 18 towns in a pilot program for the assessment.

           

Senior Site Review Ð In August, 2007, Enrique Zuniga, Director of Quality Assurance for MSBA, Joseph Miele, Senior Architect from STV, and Donald Corrie, Director of Design from STV visited Wayland High School for the Senior Site Review.  The MSBA engaged STV to provide an additional, independent analysis of the assessments done by MSBA.

 

Evaluate Potential Solutions - The Massachusetts School Building Authority (MSBA) at its Board of Directors meeting in November, 2007, invited Wayland High School to move forward to the Feasibility Study phase of applying for state funding.   There are currently  19 districts working on Feasibility/Schematics or Design Development.

 

The MSBA has defined a rolling capital pipeline of $2.5 billion spread over five years.  The MSBA will introduce projects into this pipeline as they are deemed ready.  A recent presentation by MSBA Executive Director, Katherine Craven, confirmed the commitment of $2.5 billion with a guaranteed funding floor through 2009.  The fall-off in sales tax revenue associated with the current recession will significantly affect funds available beyond 2009.  The MSBA will work with towns to agree on fiscally responsible facilities.

 

In February 2008, the MSBA laid out the next steps for Wayland as follows:

 

1.  Submit the Initial Compliance Certification (submitted in February, 2008)

2.  Form a School Building Committee (submitted paperwork in March, 2008)

3.  Complete an enrollment questionnaire (completed in April, 2008)

4.  Complete an enrollment projection working with the MSBA consultant (completed in January, 2009; MSBA and Wayland agreed on a design enrollment of 900)

5.  Procure an OwnerÕs Project Manager subject to approval by the MSBA (KVA approved by MSBA in January, 2009)

6.  Procure a Feasibility Designer through the MSBAÕs Designer Selection Panel (awaiting MSBA approval to continue with HMFH; expect approval in March, 2009)

7.  Execute a Feasibility Study Agreement with the MSBA detailing scope, schedule, milestones and cost-sharing parameters of the Feasibility Study/Schematic Design (expecting to sign agreement after April, 2009 Annual Town Meeting)

8.  Execute Project Scope and Budget Agreement including schedule, price, and MSBA participation (projected for Fall 2009)

9.  Conduct a local vote on project (projected for November, 2009)

10. Execute Project Funding Agreement (projected for November, 2009)

 

Feasibility Study/Schematic Design

Wayland has been told by the MSBA to plan for 40% reimbursement on the Feasibility Study/Schematic Design.  The Wayland School Committee has submitted a warrant article for additional funds to complete the Feasibility Study/Schematic Design phase estimated to cost no more than $1,026,000.  Wayland voters approved $300,000 at the 2007 Annual Town Meeting in anticipation of being selected by the MSBA to proceed.  The balance of $726,000 is included in this 2009 ATM warrant.  The town is required to authorize the full amount, but the cost to the town will be no more than $315,600 after reimbursement.  (Town portion is 60% of $1,026,000 or $615,600.  Town has already appropriated  $300,000.  Balance is $315,600.)   

 

The first steps of the Feasibility Study have begun.  The Wayland School Committee engaged educational facilities planner, Dr. Frank Locker, to work with approximately 60 Wayland citizens of all ages, and teachers, administrators, and staff to plan for the future of Wayland High School.  This three-month-long effort resulted in an updated educational specification as required by the MSBA.  The revised ed spec, enrollment design number, MSBA regulations, and updated cost estimates will all be considered in analyzing options for modernizing Wayland High School.  The HSBC and MSBA will look at a variety of renovation and new construction options and come to agreement on the appropriate path.

 

Next Steps ÐThe MSBA will define the scope of a reimbursable project by considering  enrollment, square footage per student, and allowable cost per square foot.   

It is the intention of the HSBC to generate a plan for Wayland High School that will be widely supported by the taxpayers of Wayland.  Building on the consensus that something needs to be done to improve the high school facility, the HSBC will work closely with the MSBA to secure state funding and with the taxpayers of Wayland to agree on a project.  

 

Respectfully submitted,

 

Lea T. Anderson, HSBC Chairman

 

High School Building Committee Members

 

Name                          Telephone                              E-mail Address

Lea Anderson            508-358-2667                       lea@anderson.name

Josh Bekenstein       508-358-5651                       jbekenstein@baincapital.com

Dianne Bladon          508-358-0068                       dehbladon@aol.com

Steve Breit                 508-358-7966                       sbreit@alum.mit.edu

Brian Chase              508-788-1081                       abchase@comcast.net

Jim Howard               508-358-2619                       howard.james@comcast.net

Fred Knight                508-358-0834                       fred@knightway.org

David Lash                508-358-5294                       david.lash@comcast.net

Mary Lentz                 617-542-4141                       mlentz@mccallalmy.com

Joe Lewin                  508-653-9952                       joelewin@comcast.net

Cindy Lombardo       508-358-5958                       sweetlifer@aol.com

Eric Sheffels              508-358-5461                       eric.sheffels@lmp.com

Jennifer Steel            508-652-1952                       jsteel@FraminghamMA.gov