REPORT OF THE
HIGH SCHOOL BUILDING COMMITTEE
April 2008
This
update describes the work of the High School Building Committee (HSBC) during
the past year, since the Annual Town Meeting on April 29, 2007. The work of the HSBC, in prior years, is
summarized in the Report of the HSBC published in the January 2005 Special Town
Meeting Warrant. It and the more
extensive Preliminary Design Report are both available on the HSBC web site
(www.waylandschoolcommittee.org/whs/hsbc/index.htm) and at the Wayland Public
Library.
Over
the past year, the HSBC met five times for a total of 52 meetings since January
2004. These most recent meetings
focused on the state reimbursement program and community groups’ interest in
Identify the
Problem (Statement of Interest) – The Wayland School Committee and Board
of Selectmen submitted a Statement of Interest (SOI) to the Massachusetts School
Building Authority in August 2006.
There were 423 SOIs submitted from 162 districts. The SOI was the first step in the
application process for state funding.
Communities were asked to document deficiencies under eight statutory
criteria: health and safety, existing severe overcrowding, loss of
accreditation, prevention of future severe overcrowding, energy conservation
and decreased energy costs, short term enrollment growth, replacement of
obsolete buildings, and transition from court ordered racial balance districts
to walk-to districts. Wayland
documented deficiencies in seven of the eight statutory criteria.
Senior Site Review - On August 14, 2007 Enrique Zuniga, Director of
Quality Assurance for MSBA, Joseph Miele, Senior Architect from STV, and Donald
Corrie, Director of Design from STV visited
Collaborate on a
Solution - The
Massachusetts School Building Authority (MSBA) at its Board of Directors
meeting on Nov. 28, 2007, invited
The
MSBA has defined a rolling capital pipeline of $2.5 billion spread over five
years. The MSBA will introduce projects
into this pipeline as they are deemed ready.
In addition to the 83 selected, there are 45 schools on hold, which the
MSBA will work with to clarify their Statements of Interest.
On
Feb. 13, 2008, five Wayland officials (Superintendent Gary Burton, Business
Manager Joy Buhler, Town Administrator Fred Turkington, School Committee
Chairman Barb Fletcher, and HSBC Chairman Lea Anderson) met with a team of
senior officials from the Massachusetts School Building Authority. The MSBA laid out the next steps as
follows:
1. Submit the Initial Compliance Certification
2. Form a
3. Complete an enrollment questionnaire
4. Complete an enrollment projection working
with the MSBA consultant
5. Procure an Owner’s Project Manager subject
to approval by the MSBA
6. Procure a Feasibility Designer through the
MSBA’s Designer Selection Panel
7. Execute a Feasibility Study Agreement with
the MSBA detailing scope, schedule, milestones and cost-sharing parameters of
the Feasibility Study.
8. Execute Project Scope and Budget Agreement
including schedule, price, and MSBA participation.
9. Conduct a local vote on project
10.
Execute Project Funding Agreement
Wayland
has completed some of these steps already and is awaiting approval from the
MSBA on the HSBC and Designer selection (HMFH Architects). Wayland has been told by the MSBA to plan
for 40% reimbursement on the Feasibility Study. Wayland voters approved $300,000 at the 2007 Annual Town Meeting
in anticipation of being selected by the MSBA.
Those funds have not been spent and are available to begin the
Feasibility Study as soon as the state is ready.
Community
Groups – The
HSBC met with groups interested in privately funding replacement of the floor
and bleachers in the Field House, privately funding a new swimming pool, and
considering space needs for the WayCam studio in planning the high school
project. The HSBC recommends the Field
House work, as it complements the larger project. The swimming pool is being pursued as a separate unrelated
initiative from the high school project.
The HSBC will consider the needs of WayCam in planning with the state.
Next Steps – When Wayland
and the MSBA begin working on the Feasibility Study, the HSBC will begin again
to engage the community in developing a solution to the facility problems at
It
is the intention of the HSBC to generate a plan for
Respectfully
submitted,
Lea
T. Anderson, HSBC Chairman
Lea
Josh
Bekenstein 508-358-5651 jbekenstein@baincapital.com
Dianne
Bladon 508-358-0068 dehbladon@aol.com
Steve
Breit 508-358-7966 sbreit@comcast.net
Brian
Chase 508-788-1081 abchase@comcast.net
Jim
Howard 508-358-2619 howard.james@comcast.net
Fred
Knight 508-358-0834 fred@knightway.org
David
Lash 508-358-5294 david.lash@comcast.net
Mary
Lentz 617-542-4141 mlentz@mccallalmy.com
Joe
Lewin 508-653-9952 joelewin@comcast.net
Cindy
Lombardo 508-358-5958 sweetlifer@aol.com
Eric
Sheffels 508-358-5461 esheffels@aol.com
Jennifer
Steel 508-652-1952 jsteel@FraminghamMA.gov
Karen
Talentino 508-358-5961 talentino@comcast.net
Steve
Tise 508-358-0047 setarch@aol.com