Article 6
Annual Town Meeting
April 29, 2007
Mr. Moderator,
Lea Anderson
47 Sedgemeadow Rd.
As chairman of the High School Building Committee I speak in favor of Article 6. The HSBC is working to keep the project to modernize and expand Wayland High School moving forward. The Massachusetts School Building Authority, the state funding agency, is nearing the end of a four year moratorium on funding new building projects. The HSBC is committed to being ready with an application as soon as the state asks Wayland to apply. To do this, the committee respectfully requests that $300,000 be allocated for the services of our design and project management professionals to
1. analyze the MSBA regulations relative to Wayland High School’s current conditions and future needs
2. help prepare the application documents required by the state for a reimbursable project
3. help the HSBC carry out the revised charge from the Wayland School Committee
This article limits the expenditure to $75,000 to get through the pre-study phase of the state process. Only when Wayland is selected to work with the state to develop a preliminary design, will the remaining $225,000 be allocated.
First some
background:
The school was designed
in the late fifties and built in 1960 as a modular, team-teaching,
California-style campus. The
math/English building was added in 1965 and the media center was added in
1972. In 1990, WHS got an upgrade with
new roofs, some new heating and ventilation, some asbestos removal, some
improvements to classrooms and interior cosmetic renovations. Six of the eight buildings are now 47 years
old, one is 42 years old, and one is 35 years old. Even under the most
optimistic scenario, a major renovation or
new construction would not be completed before 2012. In that year, our current 3rd graders will be
freshman.
Since 2002, three
Wayland committees (including over 100 Wayland residents) and many outside
professionals have studied WHS. All
reached the same conclusion: the
facility is deficient and requires a major overhaul. However in 2003 the state building assistance
program was suspended and will not resume until this July at the earliest. Though the town voted funding for a
preliminary design in 2003, you may remember that a vote for detailed design funds
in January 2005 did not pass. The
substantial work that was done in 2004 will not go to waste. It included a detailed study of existing
conditions and educational programming, analysis of four design
approaches, all useful for following the state process.
Since the Wayland study
groups all concluded that WHS was in poor shape, there have been several
outside agencies involved as well.
In the spring of 2005,
we had our ten-year accreditation review by the NEASC. They cited Wayland High
School for lack of health and safety code compliance, overcrowding, lack of
technology infrastructure and outdated labs, undersized and overused
classrooms, and lack of handicap accessibility.
They said, “Severe limitations of the current facility seriously impact
teaching and learning.” If these
problems are not substantially addressed in the next 5 years we could be put on
probation with the potential loss of accreditation.
In the spring of 2006 a
large chunk of concrete fell off a roof overhang in a high traffic student
area. It was the result of leaky roofs
that are beyond their expected life.
Repairs were made, but problems like this will continue until a
long-term solution can be found. Other
health and safety issues include air quality, asbestos, mold, lack of
sprinklers, and poor lighting.
The Mass Division of
Occupational Safety also visited in 2006 and cited us for health and safety
issues – roof leaks, water damaged materials and air quality. These agencies, as well as the Department of
Environmental Protection, Special Education officials and local building
inspectors, will continue to watch us closely.
These problems must be
addressed. The HSBC can’t “go away” –
we’ll have to keep coming back to the town until a solution is found. We’re back now because we want to pursue
state aid for a renovation or construction project.
State process
In the past, the state reimbursed Wayland for more than half the cost of its school renovations. We were just notified that we qualify for 61% reimbursement on the last Middle School renovation. Under the new system we anticipate getting at least 40%.
The state is rolling out
a new process, and if we want that 40%, we will have to follow their
rules. The state and local community
will work together at every step of the new process. Wayland has submitted the Statement of
Interest, which is the first step. We are waiting for state approval to proceed
with the next phase – the application.
The state intends to
work closely with towns through each step but no one knows how this will
unfold. We do know that the state will
determine the scope of a reimbursable project by determining the enrollment
projection, the number of square feet per student and the cost per square foot. They will work with towns to study
alternatives, but during the preliminary design or Feasibility Study, towns
must choose one and obtain the State’s approval before proceeding.
The article before you
asks for funding to move through this Feasibility phase. We have already done a lot of work in many
areas. We think that our level of
preparation will allow us to move quickly through the process but it will
depend on the state.
One big change in the
new process has to do with the local vote.
In the past, towns could vote on multiple options or could vote design
funds only, then construction later.
Towns didn’t know their state aid percentage until after their design
was approved. Now, towns will vote on
only one approved project but will know their state aid ahead of time. Furthermore, the state will reimburse towns
on a build as you go basis, rather than reimbursing towns after the project is
completed. Therefore, towns will only
need to borrow their share of the project cost.
We will start right away
to analyze the new regulations, identify design alternatives, develop
scenarios, update cost and other assumptions, and prepare the forms and
deliverables for the state (as they become available). We have also been charged with considering a
range of design approaches with some meaningful cost alternatives.
The state could give us
the green light to prepare an application as soon as this summer, but more
likely later in the year. We want to be
ready to continue through their process without delay, so that we can submit
our application as soon as they will accept it.
There is no way to obtain state funding except to follow their
process. There are many towns eager to
move forward and if we are delayed because of funding issues in town, the state
will move on to another community.
As it is today, with the most optimistic time line, the updated WHS would start to come on line in 2012. Today’s third graders will be freshmen then. If this article does not pass that will mean further delay. As time passes, the risk increases that we will face costly temporary repairs to keep the high school going.
Last time, we started
with the optimal educational program and proposed a solution that met that
program. We also studied a minimal
“stop-gap” solution with code upgrades, designed to last 10 years. We plan to update both those scenarios. But what other scenarios should we
consider? We’ve been charged with
developing “meaningful cost alternatives”.
We will have to make trade-offs.
It is probably not
realistic to think we will discover a radically new approach, to accomplish the
optimal educational program at a lower cost.
This has been studied exhaustively by 3 committees over the past 5
years, with excellent professional help.
There’s no silver bullet.
To reduce costs, we have
to make compromises. For example, we
could have fewer classrooms, or smaller ones.
We could cut out performing arts or athletic space. We could have a smaller library or fewer
computer labs. How will we evaluate
these trade-offs? How will we prioritize
these items and assign a cost to them?
We have been and will continue reaching out to the community to engage
your help in evaluating these choices.
Will you please help us define a reimbursable plan for Wayland High
School that is widely supported by the taxpayers of Wayland?
Please start by voting
yes on Article 6.