Since the 2003 moratorium, the
Massachusetts School Building Authority (MSBA)
has developed new regulations and a new process
for working with the state to secure funding for
school projects. As part of this new process,
Wayland has submitted a Statement of Interest (SOI),
participated in a Facilities and
Maintenance Assessment, Enrollment Site Visit
and Review, and Senior Site Review and has been
selected by the MSBA, along with 49 other
schools in the state, to perform a Feasibility
Study.
Based on the MSBA's regulations, the following
steps must be performed prior to beginning the
Feasibility Study:
1. Sign Initial Compliance Certification
(complete)
2. Form School Building Committee (complete)
3. Complete Enrollment Forecast Questionnaire
(complete)
4. Complete Enrollment Projections with MSBA-assigned
consultant
5. Procure Owners Project Management based on
MSBA guidelines
6. Procure Architect based on MSBA guidelines