From the High School Building Committee
For publication in the Wayland Town Crier on Sept. 10, 2009
Contact: Lea
Anderson (lea@anderson.name)
HSBC Update
The HSBC met on September 3rd
to review cost estimates and continue developing the project budget. The team must submit the project
scope and budget to the Massachusetts School Building Authority (MSBA) on
September 8th, in preparation for a vote at the September 30th
MSBA Board meeting.
The team completed a
Schematic Design last month, which was used to prepare two independent cost
estimates. This design, which is
not finalized and will continue to be refined and modified, assumes 159,000
square feet of new construction.
The target square footage approved by the MSBA is 154,350. Steve Millington, project architect
from HMFH, will continue to work to reduce the square footage to the
target.
The design also makes many
conservative assumptions about the reuse of existing equipment and furnishings,
and allowances for items that might later be reduced or deleted. This was done to make sure that
everything necessary is included in the cost estimates and to arrive at a
not-to-exceed budget. Value
engineering (i.e. finding cost
reduction opportunities) has begun and results will be presented at future
meetings.
The two cost estimates were
prepared by KV Associates (KVA), ownerÕs project manager, and by PMC, the
architectÕs independent estimator.
Frank Vanzler and David Saindon
of KVA reported that the two cost estimates were very consistent and had been
nearly reconciled. They will be
ready by the September 8th deadline.
Eric Sheffels,
HSBC member, Finance Committee appointee and president of Leggat
McCall Properties, a commercial real estate development and project management
firm, raised several questions during a detailed review of the cost estimates:
á
Do both
estimates agree on the quantities of materials to be used?
á
Are the unit
price cost assumptions reasonable?
á
Is there a
sensible contingency allowance?
á
How do the
estimates compare to other school projects?
After much discussion, the
HSBC concluded that both estimates were well done, in that there are no gaps or
holes and each line item had been considered carefully. Unit prices and contingencies are
reasonable. Assumptions made to
develop the estimate are rational.
The HSBC voted unanimously
to submit a not-to-exceed budget of $82.5 million. This budget will form the basis for discussions with MSBA
(likely the week of September 14th) about which costs are eligible for reimbursement. Some items, such as the
wastewater treatment plant and demolition of existing structures, may be
ineligible.
The next meeting of the HSBC
is scheduled for Thursday, September 17, 2009 at 7:00 pm in the School
Committee conference room on the second floor of the Wayland Town
Building. The community is invited
to all HSBC meetings. Information
is available on the HSBC website at www.waylandschoolcommittee.org/whs/hsbc/index.htm
and at the Wayland Public Library.