HSBC
Update
The
HSBC meeting on Feb. 14th covered two main topics: a review of the meeting
with the Massachusetts School Building Authority on 2/13/08 and a proposal to
do some privately funded interior work on the field house, specifically a new
floor and bleachers.
MSBA
Meeting
On
Wednesday, Feb. 13th, five Wayland officials (Dr. Gary Burton, Barb Fletcher,
Fred Turkington, Joy Buhler, Lea Anderson) met with a team of senior officials
from the Massachusetts School Building Authority. They were:
Ralph
Wallace
Director of
Capital Planning
Mary
Pichetti
Director of
Construction Management
Christine
Nolan
Associate
General Counsel
Sean
Walsh
Project Field Coordinator
Brian
McLaughlin
Legislative Liaison
George
Driscoll
Deputy
General Counsel
Ralph
Wallace reviewed the MSBA progress over the last four years including the
development of new regulations, the review of more than 420 Statements of
Interest, facilities assessments, and the selection of 83 projects into
the capital pipeline. These 83 projects are sorted as follows:
49
invited to do a Feasibility Study,
27
repair projects
7
completed or partially completed projects that will be considered for MSBA cost
sharing
Wayland
High School is one of 49 schools invited to conduct a Feasibility Study.
Ralph Wallace described the steps involved.
1.
Initial Compliance Certification must be signed. This shows that a town
is in good standing regarding audits on previous projects, and that the town
agrees to move forward in a collaborative way.
2.
School Building Committee forms. In Wayland's case, the current committee
will be reviewed by the MSBA and authorized to continue or not.
3. Town completes
a questionnaire for enrollment forecast.
4.
Enrollment projection is completed working with the MSBA
consultant.
5. Town
procures Owner's Project Manager. MSBA will provide guidelines and scope
of services.
6. Town
procures architect. Wayland has already procured HMFH Architects, Inc.
MSBA
will study Wayland's previous procurement process and authorize continuing with
HMFH or not.
7. Town
conducts Feasibility Study.
8.
Parties make agreement on budget and scope including schedule, price, and MSBA participation.
9.
MSBA Board of Directors votes on the project and scope. Town has 120 days
after this to conduct a local vote.
Wallace
said that the minimum reimbursement rate of 40% is what Wayland should use for
planning purposes on the high school project.
Field
House Floor and Bleachers
Kim
Keefer addressed the HSBC about a plan to install a new floor and bleachers in
the Field House with private funds. Kim had attended the October 18th
HSBC meeting and reported that there was a group of people in town
interested in improving the interior of the Field House and increasing gym
space. He said that the goal is to return to the original Field House
design of an open floor and improve safety. Both the floor and bleachers
are well beyond their life expectancy.
Doug
Sacra of Maple Hill Architects then presented a description of the plan to
install a new floor inside the track that would be used for practice (3 courts
or open field house), competition, and Town Meeting. He stressed
that this is a minimal project that could be completed over the upcoming
summer and early fall. Sacra and Keefer have met with school
administrators. They are approaching the HSBC now that the first meeting
with the MSBA did not uncover any reasons not to proceed. They will next
take their plan to the School Committee. They will have to meet with the
Fincom to show that the improvements will not increase maintenance costs.