Wayland, Massachusetts
FACT SHEET – Ballot Question/Warrant Article Language
The Question Why doesnÕt the ballot
question specify a dollar amount?
Why does the warrant article include the full $70.8 million? CanÕt they both specify the $45.1
additional budget being requested?
This
Fact Sheet explains the wording of the ballot question and the warrant article.
Background The High School Building
Committee (HSBC) has proposed a construction project for the modernization and
expansion of Wayland High School.
The Massachusetts School Building Authority (MSBA) approved the project
in September, and has offered a $25 million grant. Wayland voters must approve an additional project budget of
$45.1 million in order for the project to proceed. On November 17, 2009 at a Special Town Election, voters will
be asked to approve a debt exclusion to permit the town borrow funds for the
project. On November 18, 2009 at a
Special Town Meeting at 7:30 pm in the Field House at Wayland High School,
voters will be asked to approve a warrant article to appropriate the funds for
the project and to authorize the town to enter into the necessary contracts
with the MSBA.
The Budget Here is a financial
summary of the proposed project.
Total
MSBA Grant
WaylandÕs Share
Total Project
Budget $70,800,000
$25,000,000
$45,800,000
Feasibility and
Schematic
Design
Phase (1,084,812)
(433,925)
(650,887)
Remaining Phases $69,715,188
$24,566,075 $45,149,113
The
Feasibility and Schematic Design Phase has already been completed and was
funded from prior appropriations.
Net of the MSBA grant, the HSBC is seeking approval of an additional
$45.1 million in funding for the project.
Ballot The
ballot question reads, ÒShall the Town of Wayland be allowed to exempt from the
provisions of Proposition town-and-one-half, so
Question called,
the amounts required to pay for the bonds issued in order to expand and
modernize Wayland High School?Ó Massachusetts law requires this wording to
allow the Town to borrow the funds necessary for the project. The borrowing amount is not included. This requirement cannot be changed by
the Town or by the MSBA.
Warrant To
meet the requirements of the MSBA program and get the $25 million grant,
Wayland must exactly follow the MSBA form and must
Article obtain their approval on
the warrant language in advance.
The language must also conform to the applicable Massachusetts
laws. Here is an excerpt from an email sent
to HSBC chairperson Lea Anderson by Holly McClanan, an attorney with the
MSBA. Ms. McClanan says, ÒIt is essential that the Town and the voters know and understand
that Massachusetts General Laws require that the Town appropriate the total
project costs and not simply the Town's share. This is not an MSBA
requirement. Rather it is a law of the Commonwealth of Massachusetts. I have
provided the link to that statute for your convenience: http://www.mass.gov/legis/laws/mgl/44-31c.htm.Ó
She also points out that the article says the amount of borrowing will be
reduced by the grant, so the town does not have to bond the full amount.
This
means that by state law, the warrant article must specify the total project
budget, and the amount cannot be reduced to just WaylandÕs share.
The
MSBA initially specified a total budget figure of $70.8 million for the warrant
article. WaylandÕs town counsel
Mark Lanza requested that the amount be changed to the cost of the remaining
phases, $69,715,188, because the Feasibility and Schematic Design Project
funds, $1,084,812, were appropriated at earlier Town Meetings. At the time the warrant booklet was
printed, the MSBA attorney had not yet acted on this request. That is why the printed warrant shows
the full $70.8 million.
Last
week we received word that the MSBA attorney agrees with town counsel and this
change has been approved. When the
warrant article is presented at Town Meeting the amount will be $69,715,188.
Other Any
further changes that are not approved in advance by the MSBAÕs
attorney would jeopardize WaylandÕs ability to obtain the $25 million
Changes grant.
Below
is the revised text of the warrant article, as it will be presented at Town
Meeting. The only difference from
the printed warrant is the amount shown in bold.
ARTICLE 2: WAYLAND HIGH SCHOOL EXPANSION AND
MODERNIZATION
Sponsored
by: Board of Selectmen and School
Committee Estimated
cost: $69,715,188.00
To determine whether the Town will vote a.) to appropriate the sum of $69,715,188.00 to be expended under the direction of the High
School Building Committee for design, construction and other related expenses
to expand and modernize Wayland High School, 264 Old Connecticut Path, Wayland,
Massachusetts 01778, which school
facility shall have an anticipated useful life as an education facility for the
instruction of school children of at least 50 years, and for which the Town may
be eligible for a school construction grant from the Massachusetts School
Building Authority (MSBA); b.) to determine whether
such appropriation shall be provided by taxation, by transfer from unappropriated funds, by transfer of funds already
appropriated for another purpose, by borrowing under M.G.L. Chapter 44, or any
other enabling authority, or otherwise, provided that any appropriation
hereunder shall be subject to and contingent upon an affirmative vote of the
Town to exempt the amounts required for the payment of interest and principal
on said borrowing from the limitations on taxes imposed by M.G.L. Chapter 59, Section
21C (Proposition 2 1/2 ); c.) that the amount of borrowing authorized pursuant to this
vote shall be reduced by any grant amount set forth in the Project Funding
Agreement that may be executed between the Town of Wayland and the MSBA;
provided further that any grant that the Town may receive from the MSBA for said project shall not exceed
the lesser of (1) forty percent (40%) of eligible, approved project costs, as
determined by the MSBA, or (2) the total maximum grant amount determined by the
MSBA; d.) to
acknowledge that the MSBAÔs grant program is a
non-entitlement, discretionary program based on need, as determined by the
MSBA, and any project costs the Town incurs in excess of any grant approved by
and received from the MSBA shall be the sole responsibility of the Town; and
e.) to authorize the School Committee to enter into
all necessary and appropriate agreements for the design, construction and other
related expenses to expand and modernize said Wayland High School, including
but not limited to a project funding agreement and a project scope and budget
agreement with the MSBA, which agreements with the MSBA may include a provision
requiring the Town to indemnify the MSBA for losses associated with the TownÔs
performance of its obligations and exercise of its rights under such
agreements.