FACT SHEET – Alternative Projects
The Question If the proposed project is
not approved, what will be done at Wayland High School?
This
Fact Sheet explains the HSBCÕs analysis of alternative, minimum projects.
Background During the 2004
Preliminary Design Study, the High School Building Committee (HSBC) was asked
to study a minimum project that would address immediate space needs, bring the
facility up to building code and accessibility requirements, make it safe, and
keep it standing up. It would not
meet educational programming requirements. The project was called Òstop gapÓ and was estimated to cost
$37 million at the time. Details
from the 2004 study, and what was included, can be found HERE: http://www.waylandschoolcommittee.org/whs/hsbc/Documents/2004%20Preliminary%20Design%20Study/Ch-13-Stop-Gap-A.pdf.
After
the failed vote in January 2005, Turner Construction Company, then the ownerÕs
project manager, prepared a three-year plan for highest priority repairs. It is available HERE: http://www.waylandschoolcommittee.org/whs/hsbc/Web_Pages/Current_Conditions.html.
It included a recommended
list of health, safety and accessibility items with an estimated construction cost
for each item. It did not include
a project plan or schedule, nor did it include a full cost budget. (The plan has not been implemented.)
The
Scope Wayland
High School has significant facility issues, documented HERE: http://www.waylandschoolcommittee.org/whs/hsbc/Web_Pages/Current_Conditions.html. The Turner Report listed these items as
highest priority: full fire protection
(sprinklers and alarms), full accessibility compliance (elevators, lifts,
ramps, door openings, plumbing fixtures, corridors and stairways), new roofs,
new windows in the Field House and window repairs in other areas, hazardous
materials remediation (asbestos and lead paint), new carpeting, new doors and
hardware (due to corrosion), hazardous waste disposal per DEP orders, HVAC and
plumbing repairs and upgrades, electrical system upgrades, and technology/communications
upgrades. The Òstop gapÓ project
included all of this, as well as these items required by codes and
regulations: Title 9 compliance
(girls locker room addition), storm water management for all parking lots, new
waste water treatment plant, and structural work for seismic codes. ÒStop gapÓ also included new science
labs and other classroom space, but no enlargement or reconfiguration of
existing classrooms.
Stop Gap During
the recently completed Feasibility Study, the HSBC again studied the same Òstop
gapÓ project, updated for current building codes and standards. ÒStop gap,Ó
unlike the other options studied, would not meet educational programming
requirements. It also would not
meet the Massachusetts School Building Authority (MSBA) guidelines, nor address
all the issues identified during the schoolÕs accreditation review.
ÒStop
gapÓ costs were updated during the comparative cost analysis of construction
options. (According to the Turner
Construction Index, costs rose 40% from the time of the 2004 study until the
beginning of 2009, then came down 10% this year. More available HERE: http://www.turnerconstruction.com/corporate/content.asp?d=20 .)
Construction costs of Òstop gapÓ would be about 30% less than the
preferred option, though the total project costs would only be 15% less. Like the other renovation options
studied, Òstop gapÓ would take longer, be more complex and require temporary
space and multiple moves, which increases costs.
In
accordance with the MSBA grant process, no further design work was done for
Òstop gapÓ and the team proceeded with Schematic Design for the preferred
option. A full project plan and
budget was only developed for the option approved by the MSBA. Based on that budget, KV Associates,
now the ownerÕs project manager, estimates that the total project budget for
Òstop gapÓ would today be $62.3 million.
Incremental If
the proposed project is not approved, the facility issues must still be
addressed. Wayland will face
Repairs significant
capital expenditures in the coming years to keep the school operational and
accredited. However, there are an
infinite number of possible repair projects. Which items would be addressed, and in what order, and over
what time frame? Even a smaller
renovation project could trigger requirements to bring the entire facility up
to current codes and standards.
For example, spending $14 million over 3 years would require full
accessibility compliance for the entire facility. Without a project plan, an analysis of applicable codes and
discussions with permitting authorities, other triggers cannot be
estimated. Establishing a cost for
the Òincremental repairsÓ approach will require additional planning and
analysis, as well as funding for professional input.
State Aid The
$25 million grant is not transferable to an alternative project. According to the MSBA, if the proposed project
is not approved, the grant process must be repeated for an alternative project,
and reimbursement would not be at 40%, but at 31%. KVA estimates that about $11 million of Òstop gapÓ
would be excluded based on current MSBA rules, so the grant would not exceed
$16 million. Neither Òstop gapÓ
nor a more limited scope repair project would conform to the MSBA regulations
and guidelines, making any MSBA grant uncertain.
Conclusion Even
in a best-case grant scenario, the net cost of Òstop gapÓ would be $46.3
million, compared to $45.1 million for the proposed project. The cost of an Òincremental repairsÓ
approach cannot be estimated today, but the scope of such a project can grow
sizably due to codes and regulations, with little likelihood of state aid, and
deliver limited educational benefit.
Neither approach is cost-effective.