Construction Update 5-7-2012

 

The following is an overview of upcoming construction activities for the week of 5-7-12:

 

Construction crews will continue to operate Monday - Friday with occasional extended hours during the week.

 

The site contractor will start the fine grading for the asphalt at the parking areas, asphalt binder will begin at the end of the week and will continue into the next week.  

 

The roofer and Zinc installers will start work on the canopy weather permitting.

 

The landscaper will continue to place loam at the leaching fields, rain gardens, and new meadows by the tennis courts.

 

The site contractor will start removing old temporary hardscaping at the east side of the Field house and start installation of underground electrical for lights.

 

Town Water Dept will be onsite working on the water line to accommodate drainage and new service.

 

We apologize for any inconvenience caused by construction activities.