High School Building Project
Construction Update for Week of 4-17-2012
The following
is an overview of upcoming construction activities for the week:
Construction
crews will continue to operate Monday - Friday with occasional extended hours
during the week.
The site
contractor will continue to rough grade the site, install rain gardens, install
dense grade for temp parking lot, tie in the sewer
from the field house to the WWTP.
The masons
will continue working on the clock tower and brick should be wrapping up by the
end of the week.
The sound
isolation work and some smaller misc work will be conducted during April
vacation inside the new buildings.
Town Water
Dept will be onsite working on the water line to accommodate drainage and new
service.