Wayland High School Construction Update
Week of 5/9/2011
The following is an overview of construction activities for the
coming week:
The site will be closed on Saturday 5/7/2011 for
SATs (good luck!) but open on Saturday 5/14/2011
Buildings A & B - Construction activities
this week will be similar to last week, with exterior masonry and
metal siding. curtain wall at Building B,
interior drywall at both buildings and MEP rough-in. Interior finish work has begun; we have started painting and
ceramic tile and are delivering acoustic tile ceiling grid materials next week.
Wastewater treatment plant
- Exterior masonry wall
construction will continue as well as interior under slab conduit installation.
With the road at the corner near the Math/English building being
split, we remind drivers and pedestrians to be extra careful
when moving through this area.
Fieldhouse - Skylight
replacement is ongoing as well as exterior
soffit framing. We will also place concrete for the lower level
locker room floor slab during the week. We are also framing interior walls
and installing rough MEP systems. The Fieldhouse will continue
to be off-limits to non-construction personnel
throughout the construction phase. Construction fencing is in
place to secure this work area.
Temporary construction lighting will
NOT be shut off at night; the lights will remain on to deter trespassing and
vandalism.
Looking ahead to Summer 2011, we are
planning the following activities to start as soon as school ends:
- Pool parking lot redevelopment, this parking lot will be closed for
construction for the duration of the summer break
- Site utility services under the driveway up to the wastewater treatment plant
- this work will require us to close the driveway and any access to the rear
parking lots for most of the summer break
We apologize for any inconvenience resulting from
these activities.
Regards,
Chris Semlies
Shawmut Design and Construction