HSBC Construction Update

Week of March 7, 2011

 

The following is an overview of construction activities for the coming week:

      The site will be open on Saturday 3/5/2011 as well as Saturday 3/12/2011

      Buildings A & B - Construction activities this week will be similar to last week, with exterior framing, sheathing and waterproofing as well as roofing at Building A. Exterior masonry work and interior framing and MEP rough-in will continue at Building B  and masonry will start at Building A.  We plan a concrete placement at Building A on Tuesday. This work will continue until approximately 9 pm similar to prior concrete placements. The temporary heating systems at both Buildings A and B will run continually to support the concrete slab and masonry work.   Windows are being delivered for Building B on Tuesday. 

       Wastewater treatment plant  - We will have a  crane on site  on  Tuesday to set the  last remaining underground tank. Access on the temporary road in this area will be maintained. Please note that, in late March, we will need to shift the temporary road closer to the Math/English building in order to construct the plant building itself. More information to follow in future updates. 

      Fieldhouse  - We will continue demolition work at the  Fieldhouse  throughout the week.   The Fieldhouse will continue to be off-limits to non-construction personnel throughout the construction phase. Construction fencing is in place to secure this work area.

      Temporary construction lighting will NOT be shut off at night; the lights will remain on to deter trespassing and vandalism.  

  

We apologize for any inconvenience resulting from these activities.

  

Regards,

 

Chris Semlies 

Shawmut Design and Construction