HSBC Construction Update

Week of 2-14-2011

 

The following is an overview of construction activities for the coming week:

      The site will be open on Saturday  2/12/2011  and on 2/19/2011, weather permitting. 

      Construction activities this week will be similar to last week, with exterior framing, sheathing and waterproofing as well as roofing at Building A. Exterior masonry work and interior framing and MEP rough-in will continue at Building B

      On Tuesday, we plan to place concrete  at the west portion of the Building A slab on grade, this work will continue until approx 8 pm similar to prior concrete placements.

      Masonry construction on the east and west sides  of the classroom building will continue 

      We are mobilizing the wastewater treatment plant site on Monday 2/14. Snow clearing, grading and fencing installation will take place starting on Monday. Excavation for the underground tanks will start later in the week and continue through the following week.  The temporary road will not be affected during this phase of work, although later in March we will need to shift the road closer to the Math/English building. More information to follow in future updates. 

      Temporary construction lighting will NOT be shut off at night; the lights will remain on to deter trespassing and vandalism.  

       The  temporary heating systems at both Buildings A and B will run continually  to support the concrete slab and masonry work

      We plan to start work in the Fieldhouse on Monday 2/28. As of that date, the Fieldhouse will be off-limits to non-construction personnel. Construction fencing will be installed to secure this work area. 

 

 We apologize for any inconvenience resulting from these activities.

  

Regards,

 

Chris Semlies 

Shawmut Design and Construction