Wayland High School Building Project

Construction Update week of 12-20-2010

 

The following is an overview of construction activities for the coming week:

.      The site will be closed Friday 12/24 thru Sunday 12/26

.      We are working on Saturday 12/18

.      With snow forecast for Sunday into Monday, we are planning to have manpower on site early Monday morning for snow removal so that the rest of the workers can maintain progress that day.

.      We plan to place concrete at the ground floor slab in Building B again on Tuesday or Wednesday; logistics and trucking similar to prior concrete placements.  And again, concrete finishing will continue until approximately 8:30 pm both nights.  

.      Other construction activities this week will be similar to last week, including exterior wall framing and sheathing, roofing, steel welding and bolting and installation of underground utilities. The utility work will involve periodic vibration due to soil compaction equipment.  

.      Temporary construction lighting is being shut off at night.

.      A temporary heating system is in place at Building B and will run continually.  We installed a sound baffle wall alongside the heating unit to reduce the nuisance to the neighbors.   We are going to add to this baffle to further cut down on the noise.  Unfortunately, the heaters must run continually to properly cure the concrete slabs. 

 

 

 We apologize for any inconvenience resulting from these activities.

 

Regards -

Chris