Wayland High School Building Project

Construction Update week of 11-8-2010

 

 

The following is an overview of construction activities for the coming week:

      Saturday 11/6   - We are NOT working this Saturday. 

      Steel erection will continue throughout next week at both buildings.   As everyone can see, things have taken shape quickly!

      The work day for steel will continue to run until 4:30 pm typically.  Steel deliveries will arrive daily via one to two flat-bed trailers, typically between 8 and 9 am.  

      Our first concrete slab placement is scheduled for Tuesday 11/9.  This will involve approximately 240 cubic yards of concrete being pumped to the west end of the 2nd floor of Building B.  A total of 24 concrete trucks will arrive on site in intervals throughout the morning.  Trucking should be complete at mid-day and finishing of the slabs will continue into the evening until approximately 8 pm.

      The site will be open on Thursday, Veteran's Day.

       Underground site utility work will continue daily within the construction site.   This will involve periodic vibration due to soil compaction equipment.

      Soils continue to be trucked to/from the gravel pit adjacent to the lacrosse field, so please be aware of truck traffic in that area.  Everyone should keep in mind that the gravel pit area is off limits to non-construction personnel.  We have posted signage to that effect.  Trucking is prohibited after 2:30 pm so that students can get to the field

      We will be installing masonry at the faŤade mock ups near the south wall of administration building .  

 

We apologize for any inconvenience resulting from these activities.  

 