Wayland High School Building Project

Construction Update week of October 31, 2010

 

Happy Halloween!

 

 

The following is an overview of construction activities for the coming week:

      Saturday 10/30  - We are working this Saturday  - steel erection only. 

      Steel erection will continue throughout next week at both buildings  As everyone can see, things have taken shape quickly! 

      The work day for steel will continue to run until 4:30  pm typically.  Steel deliveries will arrive daily via one to two flat-bed trailers, typically between 8 and 9 am.  

      We are also preparing the west end of the 2nd floor of Building B for the first concrete slab placement.  This will take place late in the week or early the following week.

      Underground site utility work will continue daily within the construction site.   This will involve periodic vibration due to soil compaction equipment.

      Soils continue to be trucked to/from the gravel pit adjacent to the lacrosse field, so please be aware of truck traffic in that area.  Everyone should keep in mind that the gravel pit area is off limits to non-construction personnel.  We have posted signage to that effect.  Trucking is prohibited after 2:30 pm so that students can get to the field

      We will be installing masonry at the faŤade mock upnear the south wall of administration building .  

 

We apologize for any inconvenience resulting from these activities.  

 

Regards -

Chris