Wayland High School Building Project
Construction Update week of October 31, 2010
Happy Halloween!
The following is an overview of construction
activities for the coming week:
Saturday 10/30 - We are working this Saturday - steel erection only.
Steel erection
will continue throughout next week at both buildings. As everyone can see,
things have taken shape quickly!
The work day for steel will continue to run until 4:30
pm typically. Steel deliveries will arrive daily via one to
two flat-bed trailers, typically between 8 and 9
am.
We are also preparing the west end of
the 2nd floor of Building B for the first concrete slab
placement. This will take place late in the week or early the
following week.
Underground site utility work will continue
daily within the construction site. This will involve periodic
vibration due to soil compaction equipment.
Soils continue to be trucked to/from the gravel pit
adjacent to the lacrosse field, so please be aware of truck traffic in that
area. Everyone should keep in mind that the gravel pit area is off limits
to non-construction personnel. We have posted signage to that
effect. Trucking is prohibited after 2:30 pm so that students can
get to the field
We will be installing masonry at
the faŤade mock ups near the south
wall of administration building .
We apologize for any inconvenience resulting
from these activities.
Regards -
Chris