Wayland High School Building Project
Construction Update week of 10/11/2010
The following is an overview of construction
activities for the coming week:
First, the good news... Erection of structural
steel at Building B is underway!.
This work will continue for several weeks. The work
day for this activity will extend until 5 pm typically.
Underground site utility work will continue
daily within the construction site, specifically in the areas closest to
the History Building, Administration Building, and near the construction
trailers. This will involve periodic vibration due to soil compaction
equipment.
Soils continue to be trucked to/from the gravel pit
adjacent to the lacrosse field, so please be aware of truck traffic in that
area. Everyone should keep in mind that the gravel pit area is off limits
to non-construction personnel. We have posted signage to that
effect. Trucking is prohibited after 2:30 pm so that students can
get to the field
Continuation of activities related to the
construction of faŤade mock up near the south wall of administration building
We apologize for any inconvenience resulting
from these activities.
Regards -
Chris