Thursday, August 27, 2009
Wayland Town Building
School Committee Conference Room
Attendees
HSBC members:
Lea Anderson, Josh Bekenstein, Dianne Bladon, Jim Howard, David Lash,
Mary Lentz, Joe Lewin, Cindy Lombardo, Eric Sheffels
Absent: Brian Chase, Fred Knight, Jennifer Steel
HMFH Team:
Steve Millington
KVA Team: David Saindon, Frank Vanzler
Ex Officio members: Gary Burton, Louis Jurist, John
Moynihan, Pat Tutwiler
Call to order Ð HSBC Chairman, Lea Anderson, called the
HSBC meeting to order at 6:15 p.m.
Project update -
David Saindon, Project Manager, reviewed the activity of the past two
weeks:
Site/Landscape review Ð David explained that the site/landscape
review will be rescheduled for a future meeting.
Presentation of initial cost estimates Ð Frank Vanzler and David Saindon discussed
the cost estimating process. Frank
reported that they were given a very good set of schematics and specs, and good
cooperation from the consultants.
The two estimates are about 10% apart with KVAÕs being higher. Frank explained that this is due to
about $2 million in mark-up structure (eg. contingencies) and $4 million in
direct scope elements. There is
much that has to be done in the next week to reconcile the differences. It is too early for value engineering,
but KVA will begin to work on a list of concepts to save money.
David said that
MSBA wants to see the two initial estimates as well as the final reconciled
estimate. He will deliver the
initial estimates on August 31st and the reconciled estimate on
September 8th.
Discussion
followed:
á
WWTP (waste
water treatment plant) costs include the building and everything in it, outflow
and leaching field.
á
Site work
cost is higher than MSBA allowance (8% of building cost).
á
When
talking about cost per square foot, be careful to know what we are talking
about (total project, hard costs only?).
á
Is there
town insurance for Òoutside the fenceÓ?
John Moynihan will talk to David about this.
á
We should
carry a budget for legal fees.
á
Lessons
learned from the middle school were underestimating asbestos abatement and
waste water treatment.
á
Utility
tunnels need abatement. (This will be covered in the final asbestos abatement
report. The estimate for abatement
is adequate to address this.)
á
Is rental
of trailers included? (Contractor
pays)
á
Field house
renovation cannot be completed over a summer. David will talk to Martha Jamieson about carrying on the
program during renovation.
á
We need to
look at cost in some context such as background information of other high
school projects. Project funding agreements
for other projects are public information.
á
Hanover
project cost is $376 per square foot.
Wellesley came in at $466 but was cut back to $392 per square foot for
MSBA funding purposes.
á
Cost
estimate for new construction should be a total, not separate numbers for each
building.
á
MSBA and
Wayland will agree on a budget. We
will look to HMFH and KVA to build a school for that amount.
á
DonÕt
forget to budget for separate reviews for building commissioner.
á
Frank asked
the committee to e-mail KVA if they think of other costs that might have been
overlooked.
á
We should
articulate what we are not including (playing fields, stadium, etc.).
á
The next
steps are:
1. Reconcile the estimates
2. Look at costs
3. Make informed decisions on lowering costs
The committee
agreed that Eric, Joe, and Brian (if available) will meet with HMFH and KVA on
Wednesday, Sept. 2 to review the reconciled cost estimate. John Moynihan is invited to
attend. The HSBC will meet on
Thursday, Sept. 3 to receive the reconciled estimate prior to it being
submitted to MSBA on Sept. 8. The
committee requested information on other high school projects to put the cost
numbers in context.
The committee
discussed the usefulness of bench mark information such as what was included in
the 2004 study. It is useful to
help inform the Wayland community prior to the vote as well as to prepare the
HSBC for discussions with the MSBA.
Lea reminded the group that the MSBA does not take kindly to towns
playing one project off another and that it might backfire if we take too
strong an approach in that direction.
Communities have different projects based on their programs, such as
WaylandÕs need for more science classrooms.
á 9/3: HSBC meets to recommend submitting cost estimate to MSBA
á 9/10 Ð 9/22: Special Town Meeting warrant open (placeholder article)
á week of 9/14: HSBC negotiates Project Scope and Budget Agreement with MSBA
á 9/17: HSBC must finalize proposal to present to School Committee
á 9/21: School Committee formally requests BOS to authorize debt exclusion
á week of 9/21 or 9/28: suggested HSBC briefing for BOS and FinCom
á 9/30: MSBA board vote on Wayland Project Scope and Budget Agreement; publicity on public forums released
á 9/30: tentative date for State of the Town meeting
á 10/5: Special BOS/FinCom meeting to discuss debt exclusion
á week of 10/12: Public forums
á 10/19: BOS vote to approve ballot question for debt exclusion
á week of 11/2: HSBC mailing with STM information
á 11/17: presumed date for special election for debt exclusion ballot question
á 11/18: presumed date for STM
á 11/19: STM continues if necessary
Working Groups Ð Small working groups with expertise in
specific areas will be formed to help guide the design team as the project
progresses through detailed design.
The following people ÒvolunteeredÓ to lead these groups:
Finance
Ð Mary Lentz and Josh Bekenstein
MEP
Ð Brian Chase
Landscape
and outside systems (WWTP, storm water, etc.) Ð Jennifer Steel, Fred Knight
Architectural/educational
Ð Cindy Lombardo, Jim Howard, Dave Lash, Pat Tutwiler
Communications
Ð Dianne Bladon
Cost
estimating/value engineering/contracts Ð Joe Lewin, Eric Sheffels, Brian Chase
Technology
Ð Leisha Simon and tbd
Green
design - tbd
SPED
Ð Marlene Moskowitz-Dodyk
Performance
spaces - tbd
Athletic
spaces - tbd
Motion: A motion was made
by Josh Bekenstein and seconded by Cindy Lombardo to approve the minutes to
HSBC meeting #80 held on August 13, 2009.
Vote: The motion was approved unanimously: 9 in favor, 0 against.
Adjournment Ð The HSBC adjourned at 8:30 p.m.
Next meeting Ð Thursday, September 3 at 7:00 pm in the
School Committee conference room
Observers:
Sam DiSavino, Ben Foti, Kathy Siracusa
Comments from the Public: What is the status of the Math/English
building? Ans. Steve responded that the building will
most likely have to be demolished because the land is needed to meet the
parking requirements.