High School Building Committee (HSBC) Meeting #78 Minutes
Thursday, July 16, 2009
Wayland Town Building
School Committee Conference Room
Attendees
HSBC members:
Lea Anderson, Josh Bekenstein, Brian Chase, Jim Howard, Fred Knight,
David Lash, Joe Lewin, Mary Lentz, Eric Sheffels, Jennifer Steel
Absent: Dianne Bladon, Cindy Lombardo
HMFH Team:
George Metzger, Steve Millington
KVA Team: David Saindon
Ex Officio members: Gary Burton, Louis Jurist, Allyson
Mizoguchi, Pat Tutwiler
Call to order Ð HSBC Chairman, Lea Anderson, called the
HSBC meeting to order at 7:40 p.m.
Project Update -
David Saindon, Project Manager, reviewed the activity of the past two
weeks:
- David and Lea met with John Jumpe,
Katie DiCristofaro, and Carl Brown of MSBA on July 13th. Wayland received confirmation on
the following points:
- MSBA directed Wayland to design
154,350 square feet of new construction.
- MSBA will participate in a
renovated field house that corresponds to the cost equivalent of 19,800
s.f. minus 3,150 s.f. of new construction or 16,650 square feet.
- MSBA will not participate in
funding a WWTP (waste water treatment plant), demolition of existing
buildings, swing space, or hazardous materials abatement. They also will not fund a
community cable station.
- Wayland is in the capital pipeline
and is therefore covered at 40% of the reimbursable project through
construction. The funding
floor has been lowered to 31% for future projects not in the pipeline.
- Wayland can decide to use either
Mass CHIPS or LEED standards.
The MSBA has not decided which way to go.
- Wayland can proceed with a
two-building scheme, but should expect to fund the cost premium of two
buildings vs. one building at 100%.
(The premium is currently $750,000 according to our consultants. This will be a negotiation
between Wayland and MSBA.)
- David, Steve Millington, Allyson
Mizoguchi, Gary Burton, Pat Tutwiler, Scott Parseghian, and Lea met on
July 9th to carefully review the Ed Spec. Lea reported that the meeting had
been called to make sure that nothing had been left out and to consider
priorities. Steve had said
two things that resonated with her.
First, if the architect does not receive clear direction from the
owner, then he makes logical decisions. Second, when the project is complete, owners wonder why
spaces they had before are no longer there.
Steve
was directed to make space for a large lecture hall with 100 seats. The administration felt that this space
is currently used extensively for meetings, combined classes, lectures, student
presentations, performances, drama classes, and testing. It was an oversight to leave it
out. There were additional
concerns expressed about the number of Teacher Planning Centers. An additional TPC was added. After MondayÕs MSBA meeting, Steve
revised the ed spec to come in at the bottom line number of 154,350 s.f. and
incorporated the requested changes.
He will submit the revised version to MSBA by this weekend, if the
committee agrees.
- David informed the HSBC that a
suggestion to consider saving the Math/English building for town use had
been made. The lack of
funding for demolition, the location and layout of the M/E building, and
the need for a permanent home for WayCAM all generated the beginning of
this conversation. Gary
Burton said that potential uses for the M/E building are relocation of
Central Office to free up space in the Town Building for other town uses,
space for the technology hub, WayCAM, storage, and future enrollment growth. (The M/E building is 16,537 s.f.
and was built in 1965.) Lea reported
that MSBA made it clear that any renovation of the M/E building would have
to be completely separate from the high school project. There was some discussion on the
rough cost of renovation.
- Steve reported the following:
- The WWTP engineer has put the
initial report together and submitted it to MSDP today. It includes the calculation of
the amount of waste water we need to treat. It is a request to downsize from the very high amounts
in the tables.
- Parking lots are being laid
out. If the M/E building is
demolished, there will be 80 more parking spaces. The total number of spaces should
the M/E building be saved will be around 420. Pat thinks this is enough. Steve will talk with the building inspector. Steve is assuming that the buses
will be parked off the high school site. The landscape designer is trying to save trees. Zoning requires 10% of parking
area to be planted. Civil
engineers will address storm water management.
- Geotechnical engineers should be
released tomorrow to look at foundations. Steve is working with positioning of buildings
relative to shadows.
The HSBC
commented on the current drawings as follows:
- If the geotech investigations hit
organics, there can be settling issues with the buildings.
- Try to position the buildings so
that courtyard is as big as possible.
- It is preferable to see the entrance
on the main building when driving in.
- We need an outline of specifications
on mechanical systems. Please
come to the committee for approval on this.
Ed Spec Review and Recommendation
Steve reviewed
the updated ed spec and noted that changes to the version submitted to MSBA on
June 30 are highlighted in yellow.
The changes reflect the scrubbing done last week and the direction from
MSBA to design 154,350 square feet of new construction with a renovated field
house. The major changes are:
- Large group lecture hall added at
2,250 s.f.
- Greenhouse removed at 300 s.f.
- Teacher Planning Center added at 800
s.f.
- 3rd art classroom removed
at 1200 s.f.
- Fabrication/robotics shop reduced 500
s.f. to 1,500 s.f.
- Metco office reduced, offset by
increase in academic center space
There are
additional nips and tucks.
Comments
followed:
- Pat will look at Metco
office/academic center space with Steve to see if rearranging is in order.
- Net to gross factor of 1.5 could use
a lot of space.
- Steve is still trimming. The design is still 10,000 s.f.
too big. It is part of the
process and not unusual at this stage.
- Getting to 1.5 is very difficult.
- Allyson is concerned about the
number of general use classrooms.
- We have many spaces that are new and
tie to the Futures work.
Sharing of space will be necessary when scheduling classes in the
new buildings.
- Flexibility of design is
crucial. We have to ask
ourselves what we do if enrollment goes up. Are there ways to reconfigure spaces? MSBA has the same goal.
- Specialized spaces would have to be
used for general classrooms if needed in the future.
- First challenge is, how do we get to
1.5.
- Use dotted lines to show space for
future gym.
Motion: A motion was
made by Mary Lentz and seconded by Josh Bekenstein to recommend the revised ed
spec to the Wayland School Committee.
Vote: The motion was approved unanimously: 10 in favor, 0
opposed.
Schedule Update Ð David presented an updated
schedule. He reported that
everything has been delivered to MSBA for the July 29th Board
Meeting. The public is invited to
the Board Meeting at 10 am, but there will be no presentation by Wayland. Lea, David, and Gary will attend and
welcome any other HSBC members who are interested. The committee thanked HMFH and KVA for getting this
accomplished under such a tight schedule and within the MSBA guidelines. It is a major step.
David reported
that MSBA has expressed concern about Wayland being able to submit the schematic
design deliverables by the end of August for the Sept. 30th Board
Meeting. The team will continue
working toward its goal. David is
concerned that MSBA will not be able to turn around our submittal in a month. If the Sept. 30th meeting is
not met, the schedule will slip by two months. MSBA does not meet in October, so the next meeting is at the
end of November. Joe asked David
to scrub the schedule and consider it on a day-by-day basis.
Eric reminded
the group that it will all come down to a negotiation on the bottom line price
tag.
Meeting dates are as follows:
- 7/27/09 Ð School Committee meeting
- 7/29/09 Ð MSBA Board Meeting to vote
on Wayland preferred alternative
- 7/30/09 - HSBC meeting
- 8/13/09 Ð HSBC meeting
- 8/27/09 - HSBC meeting
- 8/31/09 Ð Wayland submits schematics
package to MSBA
- 9/10/09 - HSBC meeting
- 9/24/09 - HSBC meeting
- 9/30/09 Ð MSBA Board votes on
Wayland project scope and budget
- 11/?/09 Ð Town Election and Special
Town Meeting
Lea asked the
HSBC to consider attending upcoming meetings of town boards, committees, and
other working groups with an interest in the high school project. She will work with David and Steve to
plan this.
- Conservation Commission on July 30
or August 13
- Department of Public Works on August
10
- Health Commissioners on August 18
- Planning Board on August 4 or 18
- Wellhead Protection on Thursday or
Friday mornings (to be determined)
Motion: A motion was made
by Jennifer Steel and seconded by Jim Howard to approve the minutes to HSBC
meeting #77 held on July 2, 2009.
Vote: The motion was approved unanimously: 10 in favor, 0
opposed.
Adjournment Ð The HSBC adjourned at 9:31 p.m.
Next meeting Ð Thursday, July 30 at 7:30 pm in the
School Committee conference room
Observers:
Rep. Tom Conroy, Sam DiSavino, Ken Isaacson, Joe Karbowski, Cecily
Kiefer
Comments from the Public:
Please think about saving trees that provide a screen to the neighboring
houses.