Thursday, July 2, 2009
Wayland Town Building
School Committee Conference Room
Attendees
HSBC members:
Lea Anderson, Dianne Bladon, Brian Chase, Jim Howard, Fred Knight, David
Lash, Joe Lewin, Mary Lentz, Cindy Lombardo, Jennifer Steel
Absent: Josh Bekenstein, Eric Sheffels
HMFH Team:
Steve Millington
KVA Team: David Saindon, Frank Vanzler
Ex Officio members: Gary Burton, Louis Jurist, Allyson
Mizoguchi
Call to order Ð HSBC Chairman, Lea Anderson, called the
HSBC meeting to order at 7:40 p.m.
General Project Update -
David Saindon, Project Manager, reviewed the activity of the past two
weeks:
New Construction Options Comparison Ð David reported that he and Frank
discovered a formatting error last week in the conceptual cost estimate for the
two-building scheme. The cost
premium for the two-building scheme, which had been about $50,000, is now about
$750,000 gross or about 1%. David
notified John Jumpe of MSBA as soon as he discovered the error. MSBAÕs cost estimator, Keville, also
found the mistake. The cost
estimates have been updated with new information from HMFH and their engineers
that shows cost benefits in fire code rating and grading in the two-building
option. David reported that
Keville had made some comment to MSBA that the cost delta was 10-15% between
the one and two Ðbuilding options.
While KVA has not seen the Keville report, they have checked and
rechecked the estimates and are confident that their numbers are correct and
have provided back-up material to MSBA supporting the 1% delta.
Discussion
followed:
David was
directed to ask MSBA on Tuesday to give us feedback on getting the program into
151,000 s.f. with a renovated field house.
Steve
distributed a preliminary energy analysis which compares a single building and
two-building approach. He reported
that the two-building scheme will cost slightly more than a single building or
$500 per year.
Motion: A motion was
made by Cindy Lombardo and seconded by David Lash to reaffirm the committeeÕs
decision to select the two-building scheme as the preferred option.
Vote: The motion was approved - 9 in favor, 1 opposed.
MSBA Update Ð There was little to report other than the
already discussed Feasibility Study submission. David spoke with John Jumpe earlier in the day, but received
no additional feedback. David has
requested some response from MSBA by next Wednesday so that we have something
to react to. He will call John on
Tuesday to propose coming to agreement on a total design square footage
(151,000 s.f. plus a renovated field house) and leaving the details on how to
accomplish the design to Wayland.
Committee members expressed their concern and frustration with the lack
of feedback and the risk it puts on meeting our schedule.
It was suggested
that we ask for a meeting with Mary Pichetti and that we request feedback on
the following:
It was suggested
also that we continue to stress the uniqueness of the Wayland program and that
we communicate the importance of the schedule to a vote in Wayland. We need help assessing the risk.
Review of Feasibility Study Report Ð Steve Millington reviewed the Feasibility
Study report that was submitted to MSBA this week. He explained that it is a supplement to the 2004 study. Most of the existing conditions
analysis was done in the 2004 study.
The Feasibility Study includes the new educational programming and the
preliminary option analysis and preferred option. The Budget Statement for Educational Objectives will be
included later. Appendices include
the full Existing Conditions Report of May, 2004 and the Visioning +
Educational Specifications of May, 2009 by Frank Locker. The report will be available in the
Wayland Public Library and on the HSBC website.
Steve talked
about the possible change at MSBA regarding green design. MSBA was going to take over
administration of the Mass CHPS program, but is now thinking of changing to the
LEED program administered at the national level. This will have to be sorted out soon.
Steve reported
that he is where he thought we would be at this point. The schedule is very tight to get to a
schematic design submission by the end of August. He said that all key consultants are aware of the schedule.
Motion: A motion was made
by Mary Lentz and seconded by Cindy Lombardo to approve the minutes to HSBC meeting
#76 held on June 18, 2009.
Vote: The motion was approved Ð 8 in favor; 2 abstained.
Adjournment Ð The HSBC adjourned at 9:25 p.m.
Next meeting Ð Thursday, July 16 at 7:30 pm in the
School Committee conference room
Observers:
Malcolm Astley, Enrique De Los Reyes, Kay DÕOrlando, Lori Frieling,
Linda Segal, Jeff Sklar, Robin Sklar
Comments from the Public: