High School Building Committee (HSBC) Meeting #77 Minutes

Thursday, July 2, 2009

Wayland Town Building

School Committee Conference Room

 

Attendees

HSBC members:  Lea Anderson, Dianne Bladon, Brian Chase, Jim Howard, Fred Knight, David Lash, Joe Lewin, Mary Lentz, Cindy Lombardo, Jennifer Steel

Absent: Josh Bekenstein, Eric Sheffels

HMFH Team:  Steve Millington

KVA Team:  David Saindon, Frank Vanzler

Ex Officio members: Gary Burton, Louis Jurist, Allyson Mizoguchi

 

Call to order Ð HSBC Chairman, Lea Anderson, called the HSBC meeting to order at 7:40 p.m.

 

General Project Update -  David Saindon, Project Manager, reviewed the activity of the past two weeks:

 

New Construction Options Comparison Ð David reported that he and Frank discovered a formatting error last week in the conceptual cost estimate for the two-building scheme.  The cost premium for the two-building scheme, which had been about $50,000, is now about $750,000 gross or about 1%.  David notified John Jumpe of MSBA as soon as he discovered the error.  MSBAÕs cost estimator, Keville, also found the mistake.  The cost estimates have been updated with new information from HMFH and their engineers that shows cost benefits in fire code rating and grading in the two-building option.  David reported that Keville had made some comment to MSBA that the cost delta was 10-15% between the one and two Ðbuilding options.  While KVA has not seen the Keville report, they have checked and rechecked the estimates and are confident that their numbers are correct and have provided back-up material to MSBA supporting the 1% delta.

Discussion followed:

David was directed to ask MSBA on Tuesday to give us feedback on getting the program into 151,000 s.f. with a renovated field house.

Steve distributed a preliminary energy analysis which compares a single building and two-building approach.  He reported that the two-building scheme will cost slightly more than a single building or $500 per year. 

More discussion followed:

 

 

Motion:  A motion was made by Cindy Lombardo and seconded by David Lash to reaffirm the committeeÕs decision to select the two-building scheme as the preferred option.

Vote: The motion was approved - 9 in favor, 1 opposed.

 

MSBA Update Ð There was little to report other than the already discussed Feasibility Study submission.  David spoke with John Jumpe earlier in the day, but received no additional feedback.  David has requested some response from MSBA by next Wednesday so that we have something to react to.  He will call John on Tuesday to propose coming to agreement on a total design square footage (151,000 s.f. plus a renovated field house) and leaving the details on how to accomplish the design to Wayland.  Committee members expressed their concern and frustration with the lack of feedback and the risk it puts on meeting our schedule.

 

It was suggested that we ask for a meeting with Mary Pichetti and that we request feedback on the following:

It was suggested also that we continue to stress the uniqueness of the Wayland program and that we communicate the importance of the schedule to a vote in Wayland.  We need help assessing the risk.

 

Review of Feasibility Study Report Ð Steve Millington reviewed the Feasibility Study report that was submitted to MSBA this week.  He explained that it is a supplement to the 2004 study.  Most of the existing conditions analysis was done in the 2004 study.  The Feasibility Study includes the new educational programming and the preliminary option analysis and preferred option.  The Budget Statement for Educational Objectives will be included later.  Appendices include the full Existing Conditions Report of May, 2004 and the Visioning + Educational Specifications of May, 2009 by Frank Locker.  The report will be available in the Wayland Public Library and on the HSBC website.

 

Steve talked about the possible change at MSBA regarding green design.  MSBA was going to take over administration of the Mass CHPS program, but is now thinking of changing to the LEED program administered at the national level.  This will have to be sorted out soon.

 

Schedule Update Ð David presented a detailed updated schedule.  Meeting dates are as follows:

Steve reported that he is where he thought we would be at this point.  The schedule is very tight to get to a schematic design submission by the end of August.  He said that all key consultants are aware of the schedule.

 

Motion: A motion was made by Mary Lentz and seconded by Cindy Lombardo to approve the minutes to HSBC meeting #76 held on June 18, 2009.

Vote: The motion was approved Р 8 in favor; 2 abstained.

 

Adjournment Ð The HSBC adjourned at 9:25 p.m.

 

Next meeting Ð Thursday, July 16 at 7:30 pm in the School Committee conference room

 

Observers:  Malcolm Astley, Enrique De Los Reyes, Kay DÕOrlando, Lori Frieling, Linda Segal, Jeff Sklar, Robin Sklar

 

Comments from the Public: