High School Building Committee (HSBC) Meeting #70 Minutes
Thursday, April 23, 2009
Wayland Town Building
School Committee Conference Room
Attendees
HSBC members: Lea Anderson, Josh Bekenstein, Dianne
Bladon, Brian Chase, Jim Howard, Fred Knight, David Lash, Mary Lentz, Cindy
Lombardo, Joe Lewin, Jennifer Steel
Absent: Eric Sheffels
HMFH Team: George Metzger, Steve Millington
KVA Team: David Saindon, Frank Vanzler
Ex Officio members: Gary Burton, Louis Jurist,
Allyson Mizoguchi, John Moynihan
Call to order Ð HSBC Chairman, Lea Anderson,
called the HSBC meeting to order at 7:37 p.m.
Update on MSBA Meeting 4/23 - Gary Burton, Lea Anderson, Steve
Millington, David Saindon, and Rep. Tom Conroy met with John Jumpe, Mary
Pichetti, Jennifer Conaughton (contracts) and Christine Nolan (Assoc. General
Counsel) of MSBA earlier in the day.
The purpose of
the meeting was to present Wayland High SchoolÕs educational
program and to review the latest iteration of the ed spec. David reported that we provided a substantial
package of information based on the work of the Futures Team, high school
administration, and Steve over the past few weeks. The discussion focused on academic
space. Athletics were not addressed
at this meeting. Net square footage
proposed by Wayland is currently about 6000 square feet higher than the MSBA
guidelines for non-athletic space.
Main points discussed were:
- WHS is an academic
(classical)
high school with very high participation in core academic
subjects, arts, and athletics.
- Due to high participation
level, science classroom guideline of 8 classrooms is inadequate for the
current program. Wayland needs
10.
- Vocations/Technology
guideline is too large for Wayland which does not offer vocational
courses.
- Due to high participation
level, music at WHS requires two rooms Ð one for band and another for
chorus/orchestra. MSBA
guidelines allow only one. A
small music library for storing music is included in WaylandÕs spec.
- Art is an area that the
Futures Team identified as growing with the possible inclusion of art as a
graduation requirement.
Wayland is requesting three classrooms, one over the MSBA
guideline.
- Special Education is a fully
inclusion program at WHS. The
space allowed by MSBA is almost twice as large as Wayland needs.
- Guidance requires 8 offices,
compared with 5 in the MSBA guideline. Most Wayland students go on to
college and guidance is a critical piece of the program.
- Dining and
food services is
very undersized for WaylandÕs program. The current cafeteria is crowded
and is twice as large as the MSBA guideline.
Steve
reviewed the changes to the spec since the last meeting. The HSBC commented as follows:
- Students at WHS need spaces
to study.
- Compromises might be made
among various student study areas.
- MSBA assumes cafeteria
seatings will be equal. Our
scheduling constraints do not evenly distribute lunch seatings.
- Dr. Burton will send a
letter to DESE at the appropriate time, through MSBA, for approval of the
SPED space.
- If WaylandÕs program is 2000
square feet over, will we present a larger project to the town?
- School Committee will be
asked to weigh in. Goal is to
be within guideline in total, but if there is a critical element of the
academic program that is not being met, we should present it.
- MSBA said not to focus on
trading off delta between renovation and new construction for extra space.
- Athletics program is not yet
included in spec. All
athletics assumed to fit in Field House in this iteration. Emphasis should be placed on
researching the programmatic needs for athletics and then matching against
the existing spaces.
- Ed Spec will evolve over the
next month. DonÕt lose sight
of the big picture. We have to
figure out what kind of a project we have.
- A risk of not nailing down
the ed spec is that we end up doing too much
redesigning.
* Action
item: Steve will nail down athletic program
details with Scott and Martha so that we know what fits in the Field House and
what might be new construction (bump-out on Field House?).
George
said that high schools are struggling with the MSBA guidelines that have no
allowance for teacher offices, and space for students who are not scheduled
every minute of the day. Teachers
do not have their own rooms and must have space to prepare and meet with
students. A high school is a very
different model from an elementary school and high schools are different from
each other.
*Action item: Dr. Burton will invite John Jumpe (and
others) out to Wayland High School for a tour.
Schedule Update Ð David reviewed the
schedule adjustments. Given the
MSBAÕs board meeting dates of May 27 and July 29, and the several week lead
time to provide materials to the MSBA for review, it is clear that we cannot
make the early May submission for the May 27 board meeting. David has talked to John Jumpe about
proceeding with our refinement of the ed spec and analysis of options,
continuing to meet weekly with MSBA, and coming to a joint understanding of a
preferred option by the end of May.
As we do not want to shortchange the time for the schematic design, David
recommends that we stay with our plan to begin schematic design by the end of
May and prepare to go to the MSBA board meeting July 29 for official approval
of our selected option.
Analysis of Options
- Steve presented a refined
single phase/single building option (two-story) and presented a
ÒdiagrammaticÓ version that relates to the Futures Team
recommendations.
Refinements include a better entry, space for a future gym near the
field house.
- Next he showed a 2-building
option, similar to the selected option of 2004, relocated to the front of
the current campus, instead of behind. One building is academic space and
the other includes common space.
There is a large courtyard between the buildings, in response to
the Futures Team direction for purposeful outdoor space.
Steve
asked the group to consider directing HMFH to look at only one of these
options.
Discussion
ensued:
- Rough estimate of 10%
savings on single phase/single building is hard to ignore. This needs to be more formalized.
- Purposeful outdoor space is
an important idea from Futures report, but here is a compromise that saves
time and money. Spill out
space adjacent to commons can satisfy Futures suggestion
- Think of the academic space
we could use for the differential in cost due to phasing.
- Respond to the language of
the Futures work.
- Fresh air is unique part of
the Wayland experience. Maybe
itÕs because of the current interior condition.
- Having seen HMFHÕs Groton
Dunstable design, we should be confident that the outside will be incorporated.
- We have to prove it
out. Do the
cost estimate of both options.
- It is amazing that we are
actually accomplishing the recommendations of the Futures Team.
- The MSBA will want to see an
option similar to the renovation/new option 2 in the 2004 study
(renovation of Math/English, Admin, Arts, Field House plus new
construction).
Direction to HMFH and KVA:
- Continue to develop 3
scenarios
á
Single
building with renovated field house
á
Combination
of renovation of ÒbestÓ buildings plus new construction (comparable to 2004
option 2)
á
Renovation
of all buildings with minimal new construction
2. Do cost estimates of 5 scenarios
á
above
three
á
2-building
new construction with renovated field house
á
stop
gap
HMFH Contract Ð David reported that HMFH and the contract
sub-group had come to agreement on a fee for the Feasibility Study/Schematic
Design. The fee is within the
amount allowed through the recent appropriation at Town Meeting. The contract is the standard designer
contract required by MSBA.
Motion: A motion was made by Joe Lewin and seconded by Cindy Lombardo to
recommend to the Wayland School Committee approval of the contract and fee for
Feasibility Study/Schematic Design services by HMFH Architects in the amount of
$768,700.
Vote: The motion was approved Ð 11 in
favor; 0 opposed.
The HMFH
contract will be presented to the School Committee on April 27th. An addendum reducing KVAÕs fee by
$10,000 (from $180,395 to $170,395) will also be presented. Both consultants worked very hard to
stay within the limits set by the appropriation at Town Meeting. The HSBC expressed its appreciation.
Option Comparison Ð David presented an option
comparison tool for the group to consider when it is time to compare various
design scenarios. Suggestions for
changing the criteria and weighting were made. The group agreed to think about the form
and talk about it again. David will
send out a revised chart based on the comments he has received.
Next steps (items from KVAÕs 2-week look ahead):
1-week April 30
á
Continued
review of alternative options
á
Review
estimated cost premium of renovating all buildings
á
Review
estimated cost premium of renovating admin/media center building
á
Continued
discussion of options comparison chart
á
Recommend
approval of Feasibility Study Agreement to School Committee
2-week May 7
á
Continued
review of alternative options
á
Finalize option
comparison chart
[Week
of May 4 Ð Meet with town departments]
Schedule of meetings
April 27 Ð School
Committee meeting Ð HSBC update
April 30 Ð HSBC meeting
May 7 Ð HSBC meeting
May 14 Ð HSBC meeting
May 19 Ð Public Forum
(rescheduled)
May 21 Ð HSBC meeting
Motion: A motion was made
by Mary Lentz and seconded by Josh Bekenstein to approve the minutes to HSBC
meeting #69 held on April 16, 2009.
Vote: The motion was approved Ð 11 in
favor, 0 opposed.
Adjournment Ð The HSBC adjourned at 10:05 p.m.
Next meeting Ð Thursday, April 30 at 7:30 pm in
the School Committee conference room
Observers: Sam DiSavino, Ken Isaacson
Comments: Consider using Math/English
building for community use such as senior center, if it is not part of the
project.