HIGH SCHOOL BUILDING COMMITTEE PUBLIC FORUM
AUGUST 26, 2004
QUESTIONS, COMMENTS, AND RESPONSES
Q: The new
SBA law specifies both 25 and 30 years as the maximum borrowing period for
financing school construction. Why
this inconsistency?
A: Probably
because the law was drafted by committee.
This will be addressed in the coming months.
Q: When
preparing the financial analysis, did the HSBC take into account that SBA has a
maximum square footage it will reimburse?
A: Yes, this
was taken into account.
Q: What
factors will affect the rate of reimbursement that will be awarded under the
new SBA?
A: These are
spelled out in the new legislation and will be substantially the same as under
the old rules. They include square
footage per student, community use, and cost per square foot.
Q: I am
concerned about access and egress to the High School, as well as the amount of
parking planned. How would that
change?
A: We have
not done traffic studies but are looking for ways to improve this, such as
widening the road and including turn lanes. Unfortunately there is not a good
alternative for a second entrance to the school.
Q: Why will
it be necessary to double the number of parking spaces?
A: Because
of the new auditorium, there will be more people at the High School during
large performances and meetings.
This will result in more cars.
Q: How is
Option 3 less disruptive to students attending WHS during the renovation? It the drawings presented, it appears
that some of the new buildings encroach on existing buildings.
A: This is
the case in several of the versions weíve been studying. We are looking at the cost-benefit
trade-offs of a two-step construction strategy and might need to use modulars
for a short period of time.
Q: If the
final design of Option 3 calls for a two-step construction project, will
students be able to use the new spaces sooner?
A: Yes.
Q: Regarding
the parking spaces, is there a rule about the maximum amount of coverage that
is allowable on a site?
A: Yes,
there is a rule, but the site is so large we will be nowhere near the limit.
Q: The SBA
rules are confusing. Is there an
advantage to beginning construction before June 30, 2006?
A: The
answer is unclear. According to
the SBA legislation, projects that begin construction before June 30, 2006
would be subject to the old SBA rules.
Projects beginning after that would be subject to the new rules, which
have not yet been written. Since
we donít know what the new rules will be, itís impossible to say which rules
would be more advantageous for Wayland.
Q: Does the
SBA guarantee that a project will be reimbursed?
A: No, there
are no guarantees. Towns cannot
apply for reimbursement until the moratorium is lifted in 2007. There are three categories for
constructions projects. One, there
are projects that have been approved and are currently being funded. Two, there are some 425 projects that
have been approved and are on the waiting list to receive funding. These projects will be cleared off the
waiting list over the next three years.
Three, there are projects such as Waylandís that would have to apply
after 2007.
Q: Are we
currently being reimbursed for the Middle School project?
A: We are
approved and will receive full state reimbursement within three years.
Q: How many
projects will the SBA fund each year?
A: The new
law provides for about $500 million in grants each year, plus inflation. There will no longer be a waiting
list. Projects will only be
approved up to the amount of funding available. If a project is not approved the town will be free to apply
again the next year. No one knows
how many projects will apply in a given year. The $500 million figure was based roughly on history but it
is impossible to say what would be a ìtypicalî year.
Q: What are
the priorities for being selected for reimbursement?
A: These
have not changed, and have to do with such issues as health and safety, code
compliance and overcrowding.
Q: Has the
likelihood of reimbursement changed?
A: There
will now be an annual dollar limit for projects awarded reimbursement.
Q: Do we
have an analysis of the effect of this project on the Wayland taxpayer?
A: We are
working on this analysis but it is not yet completed.
Q: Have we
paid off the Middle School renovation?
The 1991 High School renovation?
A: The
Townís Annual Report includes a debt schedule that shows this information.
Comment: I
am a graduate of WHS and have attended all the schools in Wayland. I appreciate the work that has gone
into this project to now. When I
attended WHS, I liked the campus style and encourage you to try to preserve it
as much as possible, with criss-crossing courtyards and such. I am also concerned about the
disruption to the students attending WHS during the construction. Happy, busy kids benefit everyone who
lives in town, not just their parents.
Please be sure you take care of the kids during the construction. Another concern is access and egress to
the buildings. Please be sure the
buildings are designed so that you can get out fast in case of an
emergency. A secondary entrance to
the school should also be investigated.
We may not want traffic going through the neighborhoods adjacent to the
school, but it will be a good idea to have a locked gate for emergency access,
especially with the larger spaces being planned.
Q: Why are
the cost figures presented tonight the same as those presented on July 5th,
when further work has been done?
A: The cost
figures will continue to be refined and revised throughout the remainder of the
design project. We have presented
a snapshot of the figures the HSBC used to make their decision about a
construction option. As the figures
are revised, they will be made available to the public during the regular HSBC
meetings. Final budget figures
will be presented at the end of the design project.
Q: If we
expect state reimbursement to be based on a project around $46 million, why
didnít we instruct the architect to design a $46 million project?
A: The
charge to the HSBC was to take an educationally-based approach to the design,
so we did not establish a dollar limit and ìback intoî a design. Also, the state reimburses based on a
percentage of a construction project.
If the overall project budget were reduced, the reimbursement would also
be reduced.
Q: Can we
create a template for the tax impact, so that we can plug in different numbers
to see what the tax affect would be under various assumptions and scenarios?
A: We are
working on this, but are not ready to present figures yet because we are not
comfortable with their accuracy.
We do not want to present incorrect figures because that is
confusing. We are working with other
town boards so that we can present the best analysis possible. We will have these figures soon,
certainly before the end of the design project and well before any vote would
take place.
Q: If we
know what the educational program is, why isnít the project budget finalized?
A: The
Educational Program Specification just spells out the educational spaces, and
does not give a total building design.
(It doesnít include corridors or bathrooms, for example.) We wonít have a final figure for total
square footage until more design work is completed.
Q: I am
concerned that the same two firms presented cost figures for all three
options. What was the selection
process for choosing these firms?
Why didnít we hire additional firms to prepare more cost estimates?
A: The HSBC
went through a formal selection process to choose both the architect and
project manager, and evaluated many other firms before making a decision. In fact another firm, Dore and
Whittier, prepared cost estimates during the Feasibility Study, and their
figures are in line with the current budget figures. We didnít hire more firms because the $355,000 budget for
this project isnít enough to cover the cost of more designs.
Q: What is
the escalation figure shown on the cost slide?
A:
Escalation is inflation.
Prices are expected to change from today, so costs are typically
escalated to the midpoint of construction.
Q: Why are
so many of the buildings so close to the river? Will there be any basements?
A: No, there
will not be any basements.
Q: It seems
that Option 2 would have done more to preserve the campus style of WHS. Why wasnít it chosen over Option 3?
A: The team
felt that Option 3 was better overall for the educational program. We considered the prioritization done
by the School Administration, where the campus style was third behind health
and safety, educational spaces, and extracurricular support. We felt those factors were more
important than maintaining the campus style. However we believe Option 3 offers an opportunity for a very
attractive design, with many elements of the campus style, and hope to get the
best of all worlds.
Q: Have we
taken into account wireless technology?
Will we need computer labs?
A: We have
had some initial technology visioning meetings. We have established a budget for this, though it has been
revised and reduced. We will
continue to study this during the design.
Q: What were
the reasons the HSBC chose Option 3?
A: More
detail about the HSBCís deliberation is available in the written minutes of the
meetings, as well as in the tapes of the meetings. To summarize, the HSBC favored Option 3 because of the small
cost differential and lower risk of new construction vs. renovation, higher
quality and better support for the educational program, and the minimal
disruption during construction.
Q: How do
the projected costs compare to the benchmarks of other school projects?
A: We
studied 10 or 11 other construction projects and found that our costs were
consistent with those projects.
The Field House makes our square footage per student seem high, but not
in comparison to other schools with Field Houses.
Q: In 1998
the town placed a restriction on cell towers in Wayland. Be aware of this when you evaluate the
use of wireless technology.
A: The
technology being evaluated for wireless is different than cell tower
technology.