March 15, 2006
Ms. Janet D. Allison
New England Association of Schools & Colleges, Inc.
Commission on Public Secondary Schools
209 Burlington
Road
Bedford,
MA 01730-1433
Dear Ms. Allison:
Please
accept this letter as our April 1st, 2006 Special Progress Report
requested by the NEASC Commission. The
responses which follow are our best up-to-date answers for each of the areas
identified by the NEASC Commission in the October 21, 2005 letter sent to Wayland High School.
Before I
address the specific recommendations for each area, I would like to bring to
the Commission’s attention a dilemma faced by Wayland High School
and the Wayland community. We are
currently in the process of proposing to the community a complete facilities
renovation or construction of a new high school building. In fact, primarily due to the recent
moratorium of state assisted building funds, this proposed building project was
voted down at last year’s town meeting.
However, the documented need (as outlined in the accreditation report)
has galvanized numerous community members to continue advocating for a
significantly improved high school building.
The real hope is that a new or substantially renovated facility will be
in place by 2011 or 2012 at the latest.
Given the
prospects for a new or improved physical plant, the apparent dilemma is how to
ensure the health and safety of all our occupants while simultaneously
addressing the educational needs of students in our current building. The challenge is to identify cost-effective
ways to address the identified short-term issues while maintaining the high
quality of education, a consistent hallmark of Wayland High School. We recognize the dilemma of short-term
physical plant expenditures that are “lost” when a long-term replacement
solution is proposed. We are also keenly
aware of the need to provide both a safe and exemplary education for every
student who graduates from this high school – both now and in the future. In order to address this potential financial
conflict effectively, we are proposing that a $50,000 capital expenditure for
2007 be included in this spring’s town meeting vote. These funds will be specifically earmarked
for consultation with architects, building construction experts and others
whose advice will be needed to develop plans to address the
short-term deficiencies cited at
the high school. I am extremely pleased
to be pursuing the development of a plan, with expert advise,
that will permit us to offer a safe and comprehensive educational experience
for all of our students, both long and short-term. In keeping with NEASC Substantive Change
Policy, I will report the results of the town vote regarding this planning
capital expenditure immediately upon the completion of our April town
meeting.
The future
of Wayland High School’s physical plant will be
determined in the short-term by this upcoming vote. The long-term solution depends upon the
Wayland citizens’ willingness, along with state approval, to fund a major high
school construction project. Those who
support Wayland High School are dedicated to working
hard to make this happen. The NEASC
Commission will be kept up to date about the success of this long-term
construction effort.
I would
like to conclude this report by addressing each of the physical plant issues
identified for the Special Progress Report due by April 1st,
2006. Many of the issues identified will
be immediately addressed while others will be addressed by either the
short-term capital expenditures recommended by the architects or by a long-term
major construction project. In each area
delineated by the Special Progress Report, the goal is to address issues as
quickly as possible. Below is a list of
the immediate physical plant issues identified by the Special Progress Report
and potential short-term solutions where appropriate – an update of the progress made will
be included in the regular two-year NEASC progress report.
(1) Provide
sufficient classroom space to adequately meet the educational needs of all
students
- Opening
of two modular science classrooms – March
‘06
- Adding an additional two classrooms – converting
existing wood shop space into two functional classrooms – September ‘06
- Potential
of adding two additional modular classrooms – September ‘07
↳funds to be included in capital budget plan – must be
approved by town meeting in
April ‘07 vote
- This
will adequately meet the classroom needs for the foreseeable future given
short-term population projections
- The
long-term solution is town approval of a major renovation or new
construction of current high school facility – earliest possible
completion date 2011
(2) Provide adequate, accessible, secure, and safe storage space throughout
the facility
- Additional
storage space provided as designated by architectural review process –
funds for architectural review included in 2006 capital budget proposed to
town meeting
- Some
additional storage space provided by addition of new classrooms
- Potential
to provide sheds/trailers as additional storage space – proposed for
2007-2008 budget cycle – subject to town meeting approval
(3) Provide a facility that is fully
in compliance with all building codes
- Hire
an architectural firm to do assessment of short-term building code
compliance issues – September ‘06
↳funds included in 2006 capital budget plan – must be
approved by town meeting’s April 2006
vote
- Architecture
firm recommends a three year prioritized list which addresses building
code compliance issues, with special attention devoted to health and safety
factors – January ‘07
- The
long-term solution is town approval of a major renovation or new
construction of current high school facility – earliest possible
completion date 2011
(4) Provide a facility that is fully in compliance with ADA handicapped accessibility requirements
- ADA compliance issues addressed after short-term
architectural review report documents specific ADA compliance needs
- New
science modules meet all ADA
compliance issues
- Potential
for addition of two additional classroom modules each of which will meet
all ADA
requirements – September ‘07 – needs
town vote approval
- The
long-term solution is town approval of a major renovation or new
construction of current high school facility – earliest possible
completion date 2011
(5) Develop
and implement a plan to provide a technology infrastructure that meets the
instructional needs of students and teachers
- Long-range
technology plan has been developed by systems technology department
- Funds
expended and budgeted every year to address specific technology issues
identified by school and/or teachers (150,000 dollars planned for FY ‘07 system-wide)
- Fiber
optics connections provided for two additional high school buildings – FY 05-06
- High
school technology committee (high school teachers representing each
department and technology staff) established as an on-going review
committee
(6) Immediately
remove storage shelves and furniture that block the required thirty-six inch
egress from all classrooms and corridors
- All
egresses from classrooms will meet the thirty-six requirements – furniture
and shelves will be moved to meet this requirement
(7) Provide
contemporary science classrooms with one student lab station per student in the
class
- Two
new contemporary modular science classrooms opened – March, 2006
- Additional
funds (approximately $50,000 per year) will be included to modernize
existing science classrooms in years 2-5 of new capital budget – the
existing seven science classrooms will be renovated at the rate of two per
year starting in 2007-2008 school year
– requires town vote
- The
long-term solution is town approval of a major renovation or new
construction of current high school facility – earliest possible
completion date 2011
(8)
Provide within the facility a common space
for whole school assemblies and sufficient seating for performances and
theatrical events
- The
addition of new common space depends on town vote to renovate or build a
new high school – this new construction cannot be expected until the year
2011 at the earliest
- Provide
sufficient space to accommodate the meetings teachers have with
individuals and small groups of students
- Some
additional small meeting space for teachers and students will be provided
by the addition of four classrooms (2 new science modules and conversion
of existing woodshop into two classrooms) during the next two years and
the potential for two additional modular classrooms in year three of
capital budget. These additions
will free up additional space currently used by undersized classrooms.
- Creating
larger numbers of small meeting place will be contingent on town vote for
renovation or new building (first possible completion date is 2011)
(10) Correct the conditions
causing improper lighting, including glare
- Fifty
thousand dollars will be included in next year’s capital budget plan for
hiring architectural firm to outline a phased solution plan for building
compliance and deficiencies (e.g., lighting) at high school – requires
town vote
- The
correction of lighting deficiencies will be addressed in the review of
short-term building compliance issues by an outside architectural firm –
expected review by the end of 2006-2007 school year – requires town vote
- The
long-term solution is town approval of a major renovation or new
construction of current high school facility – earliest possible
completion date 2011
(11 & 12) Correct all electrical system deficiencies
and
correct the conditions preventing
proper air quality,
heating, and ventilation in all spaces used for instruction
- Fifty
thousand dollars will be included in next year’s capital budget plan for
hiring architectural firm to outline a phased solution plan for building
compliance and deficiencies (e.g., heating, ventilation) at high school –
required town vote
- The
correction of air quality, heating, ventilation and electrical
deficiencies will be addressed in the review of short-term building
compliance issues by an outside architectural firm – expected review by
the end of 2006-2007 school year – required town vote
(13) Correct
all athletic facilities deficiencies, including inadequate field drainage
- One
million dollars being raised privately to fund the construction of a turf
field on the site of current football field – if successful, this effort
will alleviate short-term scheduling problems for athletic fields –
proposed completion September, 2008
- The
long-term solution is town approval of a major renovation or new
construction of current high school facility – earliest possible
completion date 2011
As previously
stated, many of the proposed solutions depend on town voters approving
expenditures at town meetings. The NEASC
Commission will be kept informed about the outcomes of these votes and their
impact on the educational program at Wayland High School. If there are any additional questions, please
feel free to contact me.
Sincerely,
Charles P. Ruopp
Principal